This challenging refurbishment and fit out of the top two floors of the Nairn Building at Adam Smith College was completed successfully on a 6 week fast-track programme. The project involved the creation of cellular classrooms and staff office spaces from existing open plan spaces.
Key to the successful delivery was close co-operation with both the client and our supply chain to ensure disruption was minimised.
- Architect: CDA Architects
- Quantity Surveyor: Hardies Property & Construction Consultants